Upgrading Keystone¶
As of the Newton release, keystone supports two different approaches to upgrading across releases. The traditional approach requires a significant outage to be scheduled for the entire duration of the upgrade process. The more modern approach results in zero downtime, but is more complicated due to a longer upgrade procedure.
Note
The details of these steps are entirely dependent on the details of your specific deployment, such as your chosen application server and database management system. Use it only as a guide when implementing your own upgrade process.
Before you begin¶
Plan your upgrade:
Read and ensure you understand the release notes for the next release.
Resolve any outstanding deprecation warnings in your logs. Some deprecation cycles are as short as a single release, so it’s possible to break a deployment if you leave any outstanding warnings. It might be a good idea to re-read the release notes for the previous release (or two!).
Prepare your new configuration files, including
keystone.conf
,logging.conf
,policy.yaml
,keystone-paste.ini
, and anything else in/etc/keystone/
, by customizing the corresponding files from the next release.
Upgrading with downtime¶
This is a high-level description of our upgrade strategy built around
keystone-manage db_sync
. It assumes that you are willing to have downtime
of your control plane during the upgrade process and presents minimal risk.
With keystone unavailable, no other OpenStack services will be able to
authenticate requests, effectively preventing the rest of the control plane
from functioning normally.
Stop all keystone processes. Otherwise, you’ll risk multiple releases of keystone trying to write to the database at the same time, which may result in data being inconsistently written and read.
Make a backup of your database. Keystone does not support downgrading the database, so restoring from a full backup is your only option for recovery in the event of an upgrade failure.
Upgrade all keystone nodes to the next release.
Update your configuration files (
/etc/keystone/
) with those corresponding from the latest release.Run
keystone-manage db_sync
from any single node to upgrade both the database schema and run any corresponding database migrations.(New in Newton) Run
keystone-manage doctor
to diagnose symptoms of common deployment issues and receive instructions for resolving them.Start all keystone processes.
Upgrading with minimal downtime¶
If you run a multi-node keystone cluster that uses a replicated database, like
a Galera cluster, it is possible to upgrade with minimal downtime. This method
also optimizes recovery time from a failed upgrade. This section assumes
familiarity with the base case (Upgrading with downtime) outlined above.
In these steps the nodes will be divided into first
and other
nodes.
Backup your database. There is no way to rollback the upgrade of keystone and this is your worst-case fallback option.
Disable keystone on all nodes but the
first
node. This can be done via a variety of mechanisms that will depend on the deployment. If you are unable to disable a service or place a service into maintenance mode in your load balancer, you can stop the keystone processes.Stop the database service on one of the
other
nodes in the cluster. This will isolate the old dataset on a single node in the cluster. In the event of a failed update this data can be used to rebuild the cluster without having to restore from backup.Update the configuration files on the
first
node.Upgrade keystone on the
first
node. keystone is now down for your cloud.Run
keystone-manage db_sync
on thefirst
node. As soon as this finishes, keystone is now working again on a single node in the cluster.keystone is now upgraded on a single node. Your load balancers will be sending all traffic to this single node. This is your chance to run ensure keystone up and running, and not broken. If keystone is broken, see the Rollback after a failed upgrade section below.
Once you have verified that keystone is up and running, begin the upgrade on the
other
nodes. This entails updating configuration files and upgrading the code. Thedb_sync
does not need to be run again.On the node where you stopped the database service, be sure to restart it and ensure that it properly rejoins the cluster.
Using this model, the outage window is minimized because the only time
when your cluster is totally offline is between loading the newer version
of keystone and running the db_sync
command. Typically the outage with
this method can be measured in tens of seconds especially if automation is
used.
Rollback after a failed upgrade¶
If the upgrade fails, only a single node has been affected. This makes the recovery simpler and quicker. If issues are not discovered until the entire cluster is upgraded, a full shutdown and restore from backup will be required. That will take much longer than just fixing a single node with an old copy of the database still available. This process will be dependent on your architecture and it is highly recommended that you’ve practiced this in a development environment before trying to use it for the first time.
Isolate the bad node. Shutdown keystone and the database services on the upgraded “bad” node.
Bootstrap the database cluster from the node holding the old data. This may require wiping the data first on any nodes who are not holding old data.
Enable keystone on the old nodes in your load balancer or if the processes were stopped, restart them.
Validate that keystone is working.
Downgrade the code and config files on the bad node.
This process should be doable in a matter of minutes and will minimize cloud downtime if it is required.
Upgrading without downtime¶
Added in version 10.0.0: (Newton)
Upgrading without downtime is only supported in deployments upgrading from Newton or a newer release.
If upgrading a Mitaka deployment to Newton, the commands described here
will be available as described below, but the keystone-manage db_sync
--expand
command will incur downtime (similar to running
keystone-manage db_sync
), as it runs legacy (downtime-incurring)
migrations prior to running schema expansions.
Changed in version 21.0.0: (Yoga)
The migration tooling was changed from SQLAlchemy-Migrate to Alembic. As part of this change, the data migration phase of the database upgrades was dropped.
This is a high-level description of our upgrade strategy built around
additional options in keystone-manage db_sync
. Although it is much more
complex than the upgrade process described above, it assumes that you are not
willing to have downtime of your control plane during the upgrade process. With
this upgrade process, end users will still be able to authenticate to receive
tokens normally, and other OpenStack services will still be able to
authenticate requests normally.
Make a backup of your database. keystone does not support downgrading the database, so restoring from a full backup is your only option for recovery in the event of an upgrade failure.
Stop the keystone processes on the first node (or really, any arbitrary node). This node will serve to orchestrate database upgrades.
Upgrade your first node to the next release, but do not start any keystone processes.
Update your configuration files on the first node (
/etc/keystone/
) with those corresponding to the latest release.Run
keystone-manage doctor
on the first node to diagnose symptoms of common deployment issues and receive instructions for resolving them.Run
keystone-manage db_sync --expand
on the first node to expand the database schema to a superset of what both the previous and next release can utilize, and create triggers to facilitate the live migration process.Warning
For MySQL, using the
keystone-manage db_sync --expand
command requires that you either grant your keystone userSUPER
privileges, or runset global log_bin_trust_function_creators=1;
in mysql beforehand.At this point, new columns and tables may exist in the database, but will not all be populated in such a way that the next release will be able to function normally.
As the previous release continues to write to the old schema, database triggers will live migrate the data to the new schema so it can be read by the next release.
Note
Prior to Yoga, data migrations were treated separatly and required the use of the
keystone-manage db_sync --migrate
command after applying the expand migrations. This is no longer necessary and thekeystone-manage db_sync --migrate
command is now a no-op.Update your configuration files (
/etc/keystone/
) on all nodes (except the first node, which you’ve already done) with those corresponding to the latest release.Upgrade all keystone nodes to the next release, and restart them one at a time. During this step, you’ll have a mix of releases operating side by side, both writing to the database.
As the next release begins writing to the new schema, database triggers will also migrate the data to the old schema, keeping both data schemas in sync.
Run
keystone-manage db_sync --contract
to remove the old schema and all data migration triggers.When this process completes, the database will no longer be able to support the previous release.
Using db_sync check
¶
Added in version 12.0.0: (Pike)
Changed in version 21.0.0: (Yoga)
Previously this command would return 3
if data migrations were
required. Data migrations are now part of the expand schema migrations,
therefore this step is no longer necessary.
In order to check the current state of your rolling upgrades, you may run the
command keystone-manage db_sync --check
. This will inform you of any
outstanding actions you have left to take as well as any possible upgrades you
can make from your current version. Here are a list of possible return codes.
A return code of
0
means you are currently up to date with the latest migration script version and alldb_sync
commands are complete.A return code of
1
generally means something serious is wrong with your database and operator intervention will be required.A return code of
2
means that an upgrade from your current database version is available, your database is not currently under version control, or the database is already under control. Your first step is to runkeystone-manage db_sync --expand
.A return code of
4
means that the expansion and data migration stages are complete, and the next step is to runkeystone-manage db_sync --contract
.